Construction of 2 x ext (ext.1 = 1250m2, ext.2 = 350m2) to existing factory unit, Strabane (Groundworks)

Client - Fabplus Ltd.
Value - £100,000
Duration - 2 months
Works involved:
Setting out of works
Site clearance
  Internal & external drainage / service utility excavation / installation
R.C foundation excavation / installation
Substructure blockwork
Radon membrane installation
R.C floor construction